Hi All,
Currently I am facing a strange issue with SNC string in SU01 record.
2 jobs are scheduled as per below:
1) RSUSR300 - to update SNC name for users where it is blank
2) IDM Initial load job (scheduled to run after RSUSR300)
Whenever a new user is created, RSUSR300 job will update SNC name for the user.
However IDM initial load job is run later and removes SNC name for user.
IDM initial load job removes SNC only for newly created user (existing users - no change)
We are not able to figure out why the SNC string is overwritten by IDM job.
We have also disabled parameter for SNC name and SNC flag in all "Read user" and "Write user" passes in out Initial load job.
With SNC string overwritten by Intial Load job and making it blank causes us to manually update SNC name everyday 4 times a day.
Any suggestions on rectifying this issue?
Thanks & Regards,
V!